"We have at least 50 houses still under construction. We hope to complete these in the near future as the project comes to an end," said Chiara Camozzi, project manager for the Italian NGO, COOPI, which spearheaded the project.
Initially planned to take three years (2005-2007), the 1.5 million euro (US$2.1 million) project has stretched into 2010 due to complications, such as the post-election violence of early 2008, which affected parts of Huruma. COOPI is the project's implementing agency, with the Italian ministry of foreign affairs one of the main donors.
To begin with, the beneficiaries pay 20 percent of the cost of the house through local saving schemes, Camozzi said.
"Thereafter, they get a loan for the remaining 80 percent that they have to repay, so at the end of the process they will pay all the cost of the house," she added.
It costs at least 300,000 shillings ($3,850) to complete one house, a three-level 50 sqm structure that can be built in phases, subject to cash availability. COOPI supports the construction of the infrastructure and Pamoja Trust, a local NGO, provides social and technical support.
David Maina, 29, one of the beneficiaries of the project, cannot wait to finish paying for his two-bedroom house.
"I have about three years to go to complete payment for my home; I am looking forward to when the house will be fully complete and I will be a home-owner," he told IRIN. "I have no plans to sub-let or sell it; owning the house is a dream come true for me."
Photo: Salla Himberg/IRIN |
A view of the homes in Huruma being built under COOPI's slum upgrading project |
Brokered by COOPI and Pamoja Trust, an agreement was signed in 2002 between the Huruma community and the Nairobi City Council, with the council committing itself to transfer the land occupied by the informal settlement to the community, in accordance with a community land tenure system.
The city council also designated Huruma a "special planning area", facilitating the adjustment of conventional planning standards and the adoption of a "more appropriate" building code.
Camozzi said this was important because the application of high construction standards and the usual procedure to issue title deeds were some of the elements blamed for the failure of previous slum upgrading.
"In the past, after the redevelopment of an area and the delivery of new houses, the dynamic of the market caused the expulsion of the targeted beneficiaries, replaced by better income populations [and thus] shifting the problem from one area to another," Camozzi said.
Another slum-upgrading project is under way in Kibera, reputed to be Africa's largest informal settlement, also in Nairobi. Supported by UN-HABITAT and the World Bank Cities Alliance, the project targets thousands of slum dwellers. Already, hundreds of households have moved into improved housing units in flats built near the slum.